January to April 2010

1 March 2010

Plans finally approved – Development Application and Construction  Certificate received.

30 March 2010

Amendment submitted to council.

7 April 2010

Owner builder course completed online with Absolute Owner Builder (www.ozob.com.au)

26 April 2010

Approval of amendment received.

End April 2010

Owner Builder Permit obtained from Office of Fair Trading.

Insurances finalised (construction, public liability, workers compensation)

See The Owner Builder 158 April/May 2010 for more information on these stages.

TOB 158 April/May 2010 Building Diary