1 March 2010
Plans finally approved – Development Application and Construction Certificate received.
30 March 2010
Amendment submitted to council.
7 April 2010
Owner builder course completed online with Absolute Owner Builder (www.ozob.com.au)
26 April 2010
Approval of amendment received.
End April 2010
Owner Builder Permit obtained from Office of Fair Trading.
Insurances finalised (construction, public liability, workers compensation)
See The Owner Builder 158 April/May 2010 for more information on these stages.